Gengear Project Reference:

GE LMS100, Open Cycle Gas Turbine Power plant
2x 110MW, matched pair                                               


Project Facts at a Glance:

  • 2x GE LMS100 Open Cycle Gas Turbine Powerplants, the first matched pair in the Southern Hemisphere
  • Total Construction Management, from being handed a bare site
  • Managed up to 250x site staff and contractors
  • Practical completion achieved in just 15 months
  • Project cost USD$264 Million

Of significance construction was completed in a region with extreme rainfall and weather conditions


Project photo Gallery:

Images may take a few seconds to load